Road projects planned to accommodate Spiritwood plants

December 20, 2013 in Uncategorized

JAMESTOWN — Road improvements needed to accommodate the industrial plants planned for Spiritwood Township may amount to a total of about $14 million, according to Casey Bradley, Stutsman County auditor and chief operating officer.
Current plans ha…continue reading on thedickinsonpress.com

Road projects planned to accommodate Spiritwood plants

December 20, 2013 in Uncategorized

JAMESTOWN — Road improvements needed to accommodate the industrial plants planned for Spiritwood Township may amount to a total of about $14 million, according to Casey Bradley, Stutsman County auditor and chief operating officer.
Current plans ha…continue reading on thedickinsonpress.com

Township stands pat on $1 million permit fee for fertilizer plant

December 10, 2013 in Uncategorized

SPIRITWOOD — The planned CHS nitrogen fertilizer plant will pay about $1 million to Spiritwood Township for a building permit, if the developers proceed with construction.
The township’s board of supervisors didn’t modify the existing permit f…continue reading on thedickinsonpress.com

Construction to start on $150M ND ethanol plant

August 5, 2013 in The Dickinson Press

SPIRITWOOD Officials this week plan to start construction on an ethanol plant in southeastern North Dakota that has been in the works for two years. Continue Reading

Proposed Spiritwood plant to produce high amounts of ammonia

September 21, 2012 in The Dickinson Press

JAMESTOWN Last week’s announcement of a proposed $1.2 billion fertilizer manufacturing plant in Spiritwood begs the question of how exactly the plant will operate once construction is completed. Continue Reading

Company plans $1.2 billion project to make fertilizer at Spiritwood site

September 13, 2012 in The Jamestown Sun

Plans for a $1.2 billion fertilizer manufacturing plant at the Spiritwood Energy Park Association industrial park in Spiritwood, N.D., were announced by Gov. Jack Dalrymple and leaders of the nation’s largest farmer-owned cooperative on Wednesday. Continue Reading

Dalrymple announces $1.2B fertilizer plant: Proposed project in Spiritwood to produce 2,200 tons of ammonia daily

September 12, 2012 in The Dickinson Press

JAMESTOWN – Plans for a $1.2 billion fertilizer manufacturing plant at the Spiritwood Energy Park Association industrial park in Spiritwood were announced by Gov. Jack Dalrymple and leaders of the nation’s largest farmer-owned cooperative Wednesday. Continue Reading

Crime scene photos shown in murder trial

February 8, 2012 in The Dickinson Press

JAMESTOWN (AP) Prosecutors presented crime scene photos in the murder trial of a Jamestown woman charged with beating and stabbing to death a Somali immigrant.
Continue Reading

Avatar of WDAZ

by WDAZ

Harvest of Grief: Farmers Chip in After Family Loses 3-year-old in Accident

October 18, 2011 in WDAZ

SPIRITWOOD, N.D. More than 100 friends, neighbors and relatives harvested about 1,400 acres here Tuesday, hoping that the family who typically farms it can instead use the time to grieve. Continue Reading

Workers close to finish at Spiritwood Station

June 3, 2011 in The Jamestown Sun

Construction is wrapping up on the coal-fired power plant at the Spiritwood Industrial Park.
The process follows plans for Spiritwood Station’s commissioning and startup beginning in August.
The Great River Energy plant will produce 76 megawatts of electricity with an additional 23 megawatts during peak demands. The steam from the plant will also be used as a heat source by the Cargill Malting plant and possibly in future ethanol or bio-energy plants that could be located at the site.
Continue Reading