Highway 34 project on track for Sept. 1 opening

August 20, 2011 in Park Rapids Enterprise

Central Specialties, Inc., the Alexandria general contractor on the Highway 34 project, will receive a $120,000 incentive check if the project is completed by Sept. 1.
Make that $120,000 minus the cost of a mailbox. Continue Reading

Highway 34 construction resumes between Akeley, Nevis after hiatus

July 23, 2011 in Park Rapids Enterprise

Work resumed Thursday on the second phase of reconstruction on a stretch of Highway 34 between Park Rapids and Akeley, which will entail an unpopular 30-mile detour around Nevis. Continue Reading

Highway 34 work almost back on July 1 deadline

June 25, 2011 in Park Rapids Enterprise

Paving has begun on Highway 34 between Park Rapids and the Dorset corner and with minor exceptions, the resurfacing and turn lanes should be done by the July 1 deadline. Continue Reading

Highway 34 work starts Monday

June 4, 2011 in Park Rapids Enterprise

Highway 34 resurfacing work begins Monday in Park Rapids and the project supervisor isn’t sugar coating the initial stage, assuring that “the first mile will be ugly.” Continue Reading

Highway 34 repaving project outlined

July 31, 2010 in Park Rapids Enterprise

The Highway 34 resurfacing project from Park Rapids to Akeley is 10 months away and already drawing concerns about delays and detours.
But it is what the project won’t do that has irked local residents. Continue Reading